New to 2024

Exhibitors

Space Only Electrics

Please Note New to 2024 - Space Only Stands will not have any electrics included. Please order electrics for you stand with GES on their online portal here.

Stand Design Form

We have implemented a new stand design guide form which is to be submitted with ALL space only stand plans. Plans will not be cleared without a completed form. You are able to download this form here.

ICE Crossover

​​​​​​We have shifted iGB Affiliate London back by one day so we will now cross over with ICE for both days of the show. Please factor this in if you are servicing both shows. 

Post-show Contractor Survey

New to 2024, we will be launching a post-show contractor survey to hear your feedback on what we can do to help support you and make your lives easier at our show,. We will be mailing this out post-show. Please do keep an eye out for this - we really value feedback and will strive to initiate change based on your comments. 

Banned Materials

Clarion Gaming does not permit the following stand construction methods or materials:

  • Chipboard (unless being used as dressing only).
  • Sanding and cutting without extraction.
  • Led-based paints and primers.
  • Products containing isocyanate or labelled as H332 (harmful).

Effective immediately, Clarion Gaming is implementing further changes whereby we will no longer accept timber stand construction that does not contain prefabricated structural elements or requires excessive cutting onsite. This applies to ground mounted structures as well as rigged elements.

All timber constructions must have a timber frame built ahead of arriving within the exhibition halls comprising of connected horizontal and vertical cross-bracing. Build materials must be fit for purpose and meet fire regulations.

The cutting of timber onsite is only permitted when used for dressing only, and suitable extraction is mandatory.

This new change has been implemented to improve safety within the exhibition halls; to reduce congestion within the aisles; to ensure a more efficient and stress-free build and breakdown, and to contribute towards better sustainability within the industry. All stands must be built with safety, sustainability, and reusability in mind.

Pre-show evidence of the use of prefabrication will be required during the inspection process and prior to Clarion Gaming and their appointed stand plan inspection agency issuing provisional clearance to build. Your appointed Stand Contractor will need to provide details of how the stand will be built in line with the show timetable.

Construction will be stopped immediately if unsuitable working methods or materials are found onsite. Further sanctions may apply.